3rd phase of Biliran access road project nears completion
TACLOBAN CITY – The third phase of the P187.9-million access road project in Naval, Biliran is nearing completion, the Department of Public Works and Highways (DPWH) reported on Saturday.

DPWH Biliran Chief David Adongay Jr. said the multi-year project from 2018 to 2022 is being funded under the convergence program with the Department of Trade and Industry (DTI) that would link farm communities in the villages of Caraycaray, Cabungaan, and Libtong to the town center and nearby urban areas.
It covers a total of 5.8 km. road concreting with slope protection, masonry barriers, drainage structures, and rehabilitation of damaged pavement, with its third phase construction covering 1.86 km. of the total length now 73.41 percent complete.
Adongay said the third phase has an allocation of P46.7-million, and is expected to be finished in early January next year.
"This would provide a safer and faster transport of agricultural products for food and resource-based processing such as palay, abaca, copra, cassava, sweet potato, and ginger, among others," Adongay said in a statement.
The field office has completed the first two phases in 2018 and 2019, respectively, covering 1.6 km. of the access road.